Runway Project » Current Schedule of Activities
TWO WEEK LOOK AHEAD
Phase 1A Construction - Runway 21 Extension
Work Period: July 26, 2010 - August 8, 2010
Contract Time: Calendar Days 302-315
High Interest Items: Yes
Night Work: No
Airfield Closures: No closures, but declared distances in place -- see below regarding Work Area 3
WORK ACTIVITIES
RED = High interest
BLUE = Night work
§ Excavation & Embankment
§ Seeding & Mulching
§ Pipe Installation
§ Blasting – on-going
§ Work Inside Work Area 3 – Declared Distances in place 12 Jul – 25 Aug as follows:
RW 3 RW 21
TORA 6003’ 6003’
TODA 6003’ 6003’
ASDA 5703’ 6003’
LDA 5703’ 6003’
Note: ASDA & LDA revised from 5603’ to 5703’ Jul 21. Will revert back to 5603’ in next 1-2 weeks.