TWO WEEK LOOK AHEAD

 

Phase 1A Construction - Runway 21 Extension

Work Period: July 26, 2010 - August 8, 2010
Contract Time:   Calendar Days 302-315
High Interest Items:   Yes
Night Work:   No
Airfield Closures:   No closures, but declared distances in place -- see below regarding Work Area 3

WORK ACTIVITIES

RED =   High interest
BLUE =  Night work

§  Excavation & Embankment

§  Seeding & Mulching

§  Pipe Installation

§  Blasting – on-going

§  Work Inside Work Area 3 – Declared Distances in place 12 Jul – 25 Aug as follows:

 

             RW 3    RW 21

TORA     6003’     6003’

TODA     6003’     6003’

ASDA     5703’     6003’

LDA        5703’     6003’

 

Note: ASDA & LDA revised from 5603’ to 5703’ Jul 21. Will revert back to 5603’ in next 1-2 weeks.

 

 

For questions or complaints regarding this project, please contact Bill Pahuta, Deputy Executive Director